Project Description:
TYRINGHAM- RECONSTRUCTION OF MAIN ROAD, FROM BARNES ROAD TO MONTEREY ROAD (2.0 MILES)
The reconstruction of Main Road begins at the intersection with Monterey Road and continues southeasterly to the intersection with Barnes Road, a distance approximately 2.0 miles. The work consists of full depth roadway reconstruction, drainage system improvements, bituminous concrete berm construction, highway guard installation roadside. Horizontal widening is proposed to provide a uniform paved width of 23 feet. This paved width consists of two 10 foot travel lanes and two 1.5 foot shoulders.
Location:
  • Town of Tyringham
  • Resident Engineer: Joseph Mancari
    Construction Contract Value: $3,636,491.58
    Construction Bid Price: $3,104,694.00
    Initial Construction Estimate: $3,901,908.75
    District: District 1

    Contracts (1) Progress
    # 57073 -- Construction Contract
    Tryingham - Roadway Reconstruction and Related Work on a Section of Main Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/31/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/11/1996
    Project Status Advertised 07/19/2008
    Project Management
    100% Design 100% Package Received 09/30/1999
    100% Design 100% Package Received 10/14/2006
    100% Design 100% Package Received 07/07/2008
    100% Design 100% Package Comments to DE 01/05/2000
    100% Design 100% Package Comments to DE 08/10/2007
    100% Design 100% Package Rejected 12/01/2005
    25% Design 25% Package Received 02/10/1998
    25% Design 25% Package Comments to DE 03/20/1998
    25% Design Design Public Hearing 04/30/1998
    75% Design 75% Package Received 01/22/1999
    75% Design 75% Package Comments to DE 10/01/1999
    Final Design PS&E Received 03/10/2000
    Final Design PS&E Received 09/17/2007
    Final Design PS&E to FAPRO 01/04/2008
    Final Design PS&E to FAPRO 07/15/2008