Project Description:
ANDOVER- BRIDGE REPLACEMENT, A-09-011, STATE ROUTE 28 (NORTH MAIN STREET) OVER MBTA RR
The bridge carries Route 28 (North Main Street), an Urban Minor Arterial on the National Highway System, over the MBTA railroad tracks. The southern abutment/pier and portions of the northern abutment will be replaced. The superstructure will be replaced with a steel stringer bridge. A permanent utility bridge will carry all utilities.
Location:
  • Town of Andover
  • Construction Ends: Autumn 2019
    Resident Engineer: Robert Bosy
    Construction Bid Price: $6,953,404.10
    District: District 4
    Current Status: Current Activities: (Phase II) Contractor is preparing the roadway box for paving operations to the project limits. Contractor is tying in the new water line services and abandoning old services on the South side of the Bridge. Contractor is installing the East side bridge railing. (as of 05/28/2019)
    Additional Info: Future Activities: Phase II - Contractor will complete the remaining water line work. Contractor will remove barrier, fence and asphalt from the temporary Sweeny Court Driveway. Contractor will pave the roadway to binder grade at the project limits. Contractor will install the safety fence on the east side of the bridge. (as of 05/28/2019)

    Contracts (3) Status
    # 57463 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 88378 -- Construction Contract
    Bridge Superstructure Replacement Br. No. A-09-011 (Steel) North Main Street (Route 28) over the MBTA and Pan Am Railroads. (ABP) 22% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 12/04/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/16/1996
    Project Review Committee PRC Approved 06/12/2008
    Project Review Committee Letter 07/14/2008
    Project Status Advertised 06/06/2015
    Project Management
    100% Design 100% Package Received 02/27/2015
    25% Design 25% Package Received 03/26/2010
    25% Design 25% Package Received 09/13/2012
    25% Design 25% Package Comments to DE 04/23/2014
    25% Design 25% Package Comments to DE 07/11/2014
    25% Design Design Public Hearing 01/03/2013
    75% Design 75% Package Received 10/02/2014
    75% Design 75% Package Comments to DE 11/10/2014
    Final Design PS&E Received 05/19/2015
    Final Design PS&E to FAPRO 06/03/2015
    Consultant Contract Process Scope to DE 08/08/2008
    Consultant Contract Process NTP Issued 05/26/2009