Project Description: |
WESTON- INTERSECTION & SIGNAL IMPROVEMENTS AT ROUTE 30 (SOUTH AVE) & WELLESLEY STREET
The project limits are from High Meadow Road to DiBendedetto Drive and includes work on Wellesley Street from South Avenue to the Weston High School. The work also includes a new traffic signal system, channelization, new curbing and sidewalks. A design exception may be required for the proposed shoulder width.
|
Location: |
|
Resident Engineer: | Jahangir Rajabi Dehkharghani |
Construction Bid Price: | $1,977,761.67 |
Initial Construction Estimate: | $1,812,000.00 |
District: | District 6 |
|
Bridges |
|
|
|
|