Project Description: |
WEST BOYLSTON- WORCESTER- ROADWAY RECONSTRUCTION ON A SECTION OF MAPLE STREET
The work consists of the rehabilitation and reconstruction of Maple Street from the intersection of Burncoat Street/Tyson Road to the intersection of Shrewsbury Street, for a distance of 1315 meters in the town of West Boylston
|
Location: |
|
Resident Engineer: | Gerald Abato |
Construction Contract Value: | $1,173,953.00 |
Construction Bid Price: | $1,058,194.50 |
Initial Construction Estimate: | $1,083,153.55 |
District: | District 3 |
Current Status: | Project is substantially complete. No delays are expected. (as of 11/15/2004) |
|
Bridges |
|
|
|
|