DISTRICT 4- TRAFFIC SIGNAL BETTERMENT, VARIOUS LOCATIONS (5 SEPARATE CONTRACTS)
Location:
Resident Engineer: Ronald Baratta
Construction Contract Value: $1,223,636.00
Construction Bid Price: $378,760.00
Initial Construction Estimate: $388,000.00
District: District 4
Current Status: This contract is complete-pending finals by Resident Engineer. (as of 05/25/2006)

Contracts (1) Progress
# 31170 -- Construction Contract
TRAFFIC SIGNAL BETTERMENTS Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/16/2001
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This contract is complete-pending finals by Resident Engineer.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 09/23/2000