AMESBURY- RECONSTRUCTION OF ROUTE 150
The purpose of this project is to improve vehicular and pedestrian safety and improve vehicular capacity and traffic operations within the project limits. The portion of Route 150 included in the project limits includes a section of Hillside Avenue and Sparhawk Street from Route 110 to School Street. Greenleaf Street is also included from Sparhawk Street to Friend Street, and Highland Street from Hillside Avenue to Locust Street.
Location:
  • Town of Amesbury
  • Resident Engineer: Raymond Orsini
    Construction Contract Value: $4,773,019.00
    Construction Bid Price: $4,244,017.45
    Initial Construction Estimate: $4,001,404.00
    District: District 4

    Contracts (1) Progress
    # 82501 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Route 150 (Hillside Avenue,/Sparhawk Street) and Adjacent Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/27/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    Present Design is on hold due to public concern
    This project is on hold until abutter concerns have been addressed and sufficient town design funds are available to proceed with the design.
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/14/1996
    Project Review Committee PRC Tabled 11/11/1997
    Project Review Committee PRC Approved 07/15/1997
    Project Review Committee PRC Approved 11/12/1997
    Project Status Advertised 05/24/2014
    Project Management
    100% Design 100% Package Received 05/14/2013
    100% Design 100% Package Comments to DE 11/05/2013
    25% Design 25% Package Received 04/04/2008
    25% Design 25% Package Comments to DE 02/18/2009
    25% Design Design Public Hearing 11/05/2009
    75% Design 75% Package Received 02/10/2010
    75% Design 75% Package Comments to DE 11/01/2010
    Final Design PS&E Received 04/25/2014
    Final Design PS&E to FAPRO 05/21/2014