WORCESTER- INTERSECTION & SIGNAL IMPROVEMENTS AT LINCOLN STREET, HIGHLAND STREET, PLEASANT STREET CORRIDOR (PHASE I)
The project will improve 5 intersections: Highland at Park Ave, Lancaster St, Harvard St, Main St and Major Taylor Blvd. The project calls for making spot improvements to reduce congestion. At some locations this may involve minor widening, signal equipment upgrades & detection, lane use modifications and signal phasing. The project is intended to make safety and operation improvements and not to reconstruct the corridor.
Location:
  • City of Worcester
  • Resident Engineer: Michael Chauvin
    Construction Contract Value: $2,961,772.00
    Construction Bid Price: $2,469,647.05
    Initial Construction Estimate: $2,491,706.00
    District: District 3

    Contracts (6) Progress
    # 45572 -- Design -- Highway
    Work will consist of preparing Plans, Specifications and Estimate for intersection improvements and traffic signal upgrades for 18 locations in the City of Worcester. Final
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64319 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69763 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 78214 -- Construction Contract
    Roadway Resurfacing and Related Work (Including Traffic Signals) along Sections of Highland Street and Adjacent Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/29/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/25/1996
    Project Review Committee PRC Approved 02/25/1997
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/29/2005
    Project Status Initiated 11/29/2005
    Project Status Advertised 06/29/2013
    Project Management
    100% Design 100% Package Received 03/12/2012
    100% Design 100% Package Comments to DE 05/25/2012
    25% Design 25% Package Received 12/01/2008
    25% Design 25% Package Comments to DE 04/21/2009
    25% Design Design Public Hearing 07/14/2009
    75% Design 75% Package Received 12/01/2009
    75% Design 75% Package Comments to DE 10/22/2010
    Final Design PS&E Received 02/22/2013
    Final Design PS&E to FAPRO 06/26/2013
    Consultant Contract Process Scope to DE 06/29/2006
    Consultant Contract Process NTP Issued 05/15/2007
    Consultant Contract Process Workhours Approved 01/23/2007