Project Description:
FRAMINGHAM- RECONSTRUCTION & SIGNALIZATION OF FRANKLIN STREET, INCLUDES F-07-030
The proposed project consists of reconstructing Franklin Street from Howard Street to Main Street, in the Town of Framingham. The work will include geometric modifications, pavement rehabilitation, traffic signal installation and pedestrian safety improvements.
Location:
  • Town of Framingham
  • Resident Engineer: Alan Webb
    Construction Contract Value: $8,000,488.00
    Construction Bid Price: $7,386,321.20
    Initial Construction Estimate: $6,086,931.50
    District: District 3
    Current Status: Contructing drainage. Installing sidewalk and curbing. Signal work is continuing. Work is starting on bridge construction. (as of 09/11/2008)
    Additional Info: Delayed utility work may impact roadway widening and sidewalk placement. (as of 09/11/2008)

    Contracts (1) Progress
    # 53508 -- Construction Contract
    Framingham - Roadway Reconstruction and Related Work Including Bridge (F-07-030) on a Section of Franklin Street Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/05/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contructing drainage. Installing sidewalk and curbing. Signal work is continuing. Work is starting on bridge construction.
    Additional Info
    Delayed utility work may impact roadway widening and sidewalk placement.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/13/1996
    Project Review Committee PRC Approved 02/25/1997
    Project Review Committee PRC Approved 06/22/2004
    Project Review Committee Letter 02/25/2005
    Project Status Advertised 09/23/2006
    Project Management
    100% Design 100% Package Received 08/07/2006
    25% Design Design Public Hearing 10/28/2004
    75% Design 75% Package Received 04/07/2005
    75% Design 75% Package Comments to DE 06/29/2005
    Final Design PS&E to FAPRO 09/18/2006