Project Description:
WATERTOWN- INTERSECTION IMPROVEMENTS AT 3 LOCATIONS: SPRING AT SUMMER; MOUNT AUBURN AT SUMMER; COOLIDGE HILL ROAD AT CRAWFORD
Improvements to intersection #1 at Spring/Summer Street include 4-way stop control. Improvements to intersection #2 at Mt. Auburn/Summer Street and intersection #3 at Arlington Street/Nichols Ave./Coolidge Hill Avenue include traffic sensing devices at all four approaches. Roadway realignment will occur along the approaches for Spring Street, Crawford Street, Nichols Ave., and Arlington Street. New sidewalks with granite curbing and wheelchair ramps, as well as roadway resurfacing, will be done through all three intersections.
Location:
  • Town of Watertown
  • Resident Engineer: Anthony Digiovanni
    Construction Contract Value: $1,592,134.00
    Construction Bid Price: $1,367,224.56
    Initial Construction Estimate: $1,704,186.00
    District: District 4

    Contracts (1) Progress
    # 60199 -- Construction Contract
    Intersection Improvements and Related Work at 3 Locations. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/16/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/03/1996
    Project Review Committee PRC Approved 02/25/1997
    Project Status Advertised 08/15/2009
    Project Management
    100% Design 100% Package Received 04/06/2009
    100% Design 100% Package Comments to DE 06/12/2009
    100% Design 100% Plans Approved 06/16/2009
    25% Design 25% Package Received 10/04/2002
    25% Design 25% Package Comments to DE 05/06/2003
    25% Design Design Public Hearing 05/29/2003
    25% Design Design Public Hearing 05/14/2009
    75% Design 75% Package Received 09/14/2004
    75% Design 75% Package Comments to DE 02/04/2008
    Final Design PS&E Received 08/06/2009
    Final Design PS&E to FAPRO 08/12/2009