Project Description:
EGREMONT- BRIDGE REPLACEMENT, E-08-005, ROUTE 41 OVER KARNER BROOK
The proposed bridge replacement project will be constructed in two stages with a temporary traffic signal installed to maintain one lane of alternating traffic movements across the bridge. The new bridge will match and transition into improved roadway approaches.
Location:
  • Town of Egremont
  • Resident Engineer: Erin Cooper
    Construction Contract Value: $3,117,011.00
    Construction Bid Price: $2,629,010.40
    Initial Construction Estimate: $3,389,975.40
    District: District 1

    Contracts (4) Progress
    # 54826 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57731 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 58901 -- Construction Contract
    Bridge Replacement (E-08-005) (Concrete) Route 41 (Under Mountain Road) over Karner Brook. Completed
    # 94466 -- Design -- Footprint Bridge contracts
    CONTD FTPRT-RD3 FA NON-NHS STP Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/13/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/29/1996
    Project Review Committee PRC Approved 02/25/1997
    Project Review Committee Letter 03/21/1997
    Project Status Advertised 09/20/2008
    Project Management
    100% Design 100% Package Received 06/05/2006
    100% Design 100% Package Comments to DE 11/03/2006
    25% Design 25% Package Received 08/25/1997
    25% Design 25% Package Comments to DE 11/20/1997
    25% Design Design Public Hearing 11/09/1998
    75% Design 75% Package Received 10/20/2003
    75% Design 75% Package Comments to DE 03/15/2004
    Final Design PS&E Received 09/12/2008
    Final Design PS&E to FAPRO 09/16/2008
    Consultant Contract Process NTP Issued 05/15/2003