| Project Description: |
FAIRHAVEN- NEW BEDFORD- BRIDGE REHABILITATION, BR# F-01-002=N-06-001 ROUTE 6 OVER THE ACUSHNET RIVER
The work under this contract consists of miscellaneous repairs and replacement of structural elements for two bridges along Route 6 over the Acushnet River. The work includes repaving of the bridge and approach roadways, maintenance and protection of traffic. A significant portion of the work is beneath the bridge deck over the Acushnet River.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | Other |
| Project Manager: | John Macdonald![]() |
| Estimated Total Contract Cost: | $3,738,977.91 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 5 |
| Current Status: | This project is in the preliminary design phase. |
|