MONSON- RECONSTRUCTION OF HOSPITAL ROAD FROM MACOMBER ROAD TO PALMER ROAD (ROUTE 32) , 1.2 KILOMETERS
The project consists of the reconstruction of Hospital Road from just west of Macomber Road to the intersection with Palmer Road (Route 32), a distance of approximately 1.3 kilometers. The proposed work consists of full depth roadway reconstruction, sidewalk construction, signing and landscaping.
Location:
  • Town of Monson
  • Resident Engineer: George Pelletier
    Construction Contract Value: $1,582,828.00
    Construction Bid Price: $1,522,249.07
    Initial Construction Estimate: $1,527,016.00
    District: District 2
    Current Status: Road under construction (as of 07/21/2005)
    Additional Info: Daily lane restrictions/reductions during the work week. All lanes open at end of work day and weekends. (as of 05/01/2008)

    Contracts (1) Progress
    # 39757 -- Construction Contract
    Monson - Reconstruction of a section of Hospital Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/10/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Road under construction
    Additional Info
    Daily lane restrictions/reductions during the work week. All lanes open at end of work day and weekends.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/09/1997
    Project Review Committee PRC Approved 02/25/1997
    Project Status Advertised 09/11/2004
    Project Management
    100% Design 100% Package Received 01/27/2004
    25% Design Design Public Hearing 04/22/1999
    75% Design 75% Package Received 08/01/1999
    75% Design 75% Package Comments to DE 12/02/1999
    Final Design PS&E Received 08/05/2004
    Final Design PS&E to FAPRO 08/05/2004