Project Description:
CHESTER- BRIDGE REPLACEMENT, C-11-024, KINNE BROOK ROAD OVER MIDDLE BRANCH OF THE WESTFIELD RIVER
The proposed new bridge is on a new alignment immediately adjacent and westerly to the existing bridge. Traffic will be allowed to continue during construction on the existing bridge. Included in this project are guardrail, curbing and sediment controls for the Williams River.
Location:
  • Town of Chester
  • Resident Engineer: Richard Miskinis Jr
    Construction Contract Value: $3,140,358.00
    Construction Bid Price: $2,746,326.00
    Initial Construction Estimate: $3,097,069.00
    District: District 1

    Contracts (2) Progress
    # 32182 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract O Final
    # 53966 -- Construction Contract
    Chester - Bridge Replacement (C-11-024) - Kinne Brook Road over the Middle Branch of the Westfield River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/11/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/27/1997
    Project Review Committee PRC Approved 04/14/2003
    Project Status Advertised 09/01/2007
    Project Management
    100% Design 100% Package Received 07/27/2006
    100% Design 100% Package Comments to DE 09/12/2006
    25% Design 25% Package Received 01/27/2005
    25% Design 25% Package Comments to DE 03/11/2005
    25% Design Design Public Hearing 06/21/2005
    75% Design 75% Package Received 11/07/2005
    75% Design 75% Package Comments to DE 03/09/2006
    Final Design PS&E Received 06/22/2007
    Final Design PS&E to FAPRO 07/09/2007
    Consultant Contract Process NTP Issued 06/16/2004