Project Description: |
TAUNTON- BRIDGE REHABILITATION, BR# T-01-009 ROUTE 140 (SUMMER STREET) OVER THE BAY COLONY RAILROAD
The proposed project consists of replacement of the existing bridge superstructure with improvements to the approach roadway. The project also consists of removing the existing center pier.
|
Location: |
|
Resident Engineer: | Gary Dixon |
Construction Contract Value: | $934,618.11 |
Construction Bid Price: | $669,428.30 |
Initial Construction Estimate: | $673,692.00 |
District: | District 5 |
|