Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LYNN- RECONSTRUCTION OF ROUTE 129 (BROADWAY), FROM LYNNFIELD STREET TO CHESTNUT STREET
This project will resurface Route 129 and reconstruct sidewalks from Wyoma Square to Boston Street.
Location:
  • City of Lynn
  • Resident Engineer: Mark Spinale
    Construction Contract Value: $4,609,296.00
    Construction Bid Price: $3,959,202.00
    Initial Construction Estimate: $4,291,575.00
    District: District 4

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 79730 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) on a Section of Route 129 (Broadway). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/16/1997
    Project Review Committee PRC Approved 02/25/1997
    Project Status Advertised 09/14/2013
    Project Management
    100% Design 100% Package Received 04/09/2013
    100% Design 100% Package Comments to DE 08/06/2013
    25% Design 25% Package Received 06/27/2007
    25% Design 25% Package Comments to DE 10/24/2007
    25% Design Design Public Hearing 12/06/2011
    25% Design Design Public Hearing 07/25/2012
    75% Design 75% Package Received 04/19/2012
    75% Design 75% Package Comments to DE 07/30/2012
    75% Design 75% Plans Approved 12/07/2012
    Final Design PS&E Received 08/20/2013
    Final Design PS&E Received 09/09/2013
    Final Design PS&E to FAPRO 09/10/2013