WILLIAMSTOWN- BRIDGE REPLACEMENT, W-37-017, ROUTE 43 OVER THE GREEN RIVER
The work consists of the replacement of the Route 43 (Green River Road) bridge over the Green River with a single span concrete bridge. The proposed bridge width will be 26 feet curb to curb. Also included is roadway approach work, guardrail, pavement markings and signing.
Location:
  • Town of Williamstown
  • Resident Engineer: Glenn Cellana
    Construction Contract Value: $1,584,811.00
    Construction Bid Price: $1,369,729.00
    Initial Construction Estimate: $1,431,674.00
    District: District 1

    Contracts (2) Progress
    # 54112 -- Construction Contract
    Williamstown - Bridge Replacement (W-37-017) - Route 43 (Green River Road) over the Green River Completed
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/26/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/05/1997
    Project Review Committee PRC Approved 02/25/1997
    Project Review Committee Letter 03/21/1997
    Project Status Advertised 09/15/2007
    Project Management
    100% Design 100% Package Received 03/15/2007
    100% Design 100% Package Comments to DE 06/28/2007
    25% Design 25% Package Received 10/21/1998
    25% Design 25% Package Comments to DE 02/26/2004
    25% Design Design Public Hearing 04/29/2004
    75% Design 75% Package Received 06/01/2006
    75% Design 75% Package Comments to DE 02/28/2007
    Final Design PS&E Received 08/01/2007
    Final Design PS&E to FAPRO 09/10/2007
    Consultant Contract Process Scope to DE 07/25/1997
    Consultant Contract Process NTP Issued 02/25/1998
    Consultant Contract Process Workhours Approved 11/10/1997