Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SOMERVILLE- RECONSTRUCTION OF SOMERVILLE AVENUE FROM UNION SQUARE TO THE CAMBRIDGE LINE
The project entails the reconstruction of Somerville Avenue from the Cambridge city line across to Union Square, a length of approximately 1.32 miles. The work consists of full depth roadway construction, sidewalk reconstruction with granite curbing and wheelchair ramps, installation of new roadway drainage system, separate sewer line, replacement of old traffic signal equipment and signalization of intersections, new decorative street lighting poles, planting of new trees, installation of streetscape amenities, signing, pavement markings and landscaping.
Location:
  • City of Somerville
  • Resident Engineer: John McGillicuddy
    Construction Contract Value: $21,748,583.49
    Construction Bid Price: $20,829,736.00
    Initial Construction Estimate: $18,101,921.00
    District: District 4

    Contracts (1) Progress
    # 50120 -- Construction Contract
    Somerville - Roadway Reconstruction and Related Work on a Section of Somerville Avenue Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/05/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 02/25/1997
    Project Status Advertised 09/17/2005
    Project Status Advertised 09/23/2006
    Project Management
    100% Design 100% Package Received 08/16/2005
    25% Design 25% Package Received 03/26/2003
    25% Design Design Public Hearing 08/30/2005
    75% Design 75% Package Received 07/13/2003
    75% Design 75% Package Comments to DE 12/05/2003
    75% Design 75% Package Rejected 12/22/2004
    Final Design PS&E Received 09/08/2005
    Final Design PS&E to FAPRO 09/08/2005