Project Description:
CHICOPEE- RECONSTRUCTION OF FRONT STREET
The scope of work consists of pavement reconstruction as well as reconstruction of sidewalks and wheel-chair ramps and a reconfiguration of the intersection of Front Street and Grove Avenue. Improvements to the existing traffic signal are proposed for the intersection of Front Street and Grape Street. Safety improvements such as signing and pavement markings will be part of this project.
Location:
  • City of Chicopee
  • Resident Engineer: Joseph Gaudet Jr
    Construction Contract Value: $9,181,492.00
    Construction Bid Price: $8,449,457.00
    Initial Construction Estimate: $9,146,840.00
    District: District 2

    Contracts (1) Progress
    # 56479 -- Construction Contract
    Chicopee - Roadway Reconstruction and Related work on Front Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/07/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/07/1997
    Project Review Committee PRC Approved 05/06/1997
    Project Status Advertised 05/31/2008
    Project Management
    100% Design 100% Package Received 06/22/2005
    100% Design 100% Package Comments to DE 09/15/2006
    25% Design Design Public Hearing 03/30/1999
    75% Design 75% Package Received 07/07/2004
    75% Design 75% Package Comments to DE 12/16/2004
    Final Design PS&E Received 12/11/2007
    Final Design PS&E to FAPRO 12/21/2007