Project Description: |
CHICOPEE- RECONSTRUCTION OF FRONT STREET
The scope of work consists of pavement reconstruction as well as reconstruction of sidewalks and wheel-chair ramps and a reconfiguration of the intersection of Front Street and Grove Avenue. Improvements to the existing traffic signal are proposed for the intersection of Front Street and Grape Street. Safety improvements such as signing and pavement markings will be part of this project.
|
Location: |
|
Resident Engineer: | Joseph Gaudet Jr |
Construction Contract Value: | $9,181,492.00 |
Construction Bid Price: | $8,449,457.00 |
Initial Construction Estimate: | $9,146,840.00 |
District: | District 2 |
|