Project Description: |
AMHERST- TRAFFIC SAFETY IMPROVEMENTS INCLUDING SIGNALS, ROUTE 9 (BELCHERTOWN ROAD) AT OLD FARM ROAD AND GATEHOUSE ROAD
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Other |
Project Manager: | Peter Kutrubes |
Estimated Total Federal Participating Construction Cost: | $150,000.00 |
District: | District 2 |
Current Status: | This project has been advertised for construction bids. (as of 01/12/2002 ) |
|