Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LEXINGTON- SIGNAL UPGRADE AT ROUTE 2A AND WALTHAM STREET
The proposed project at the intersection of Route 2A (Marrett Road) and Waltham Street improves the safety of pedestrians and vehicles through the reconstruction of traffic signals and sidewalks. Additional work includes pavement resurfacing, minor pavement widening, new pavement markings, signing, and minor landscaping.
Location:
  • Town of Lexington
  • Resident Engineer: Martin McGowan
    Construction Contract Value: $1,839,557.00
    Construction Bid Price: $1,527,915.96
    Initial Construction Estimate: $1,862,329.00
    District: District 4

    Contracts (2) Progress
    # 64325 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 66334 -- Construction Contract
    Intersection Improvements and Related Work )Including Traffic Signal Upgrades) Route 2A (Marrett Road) at Waltham Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/26/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/11/1997
    Project Review Committee PRC Approved 05/06/1997
    Project Status Advertised 07/24/2010
    Project Management
    100% Design 100% Package Received 12/22/2009
    100% Design 100% Package Comments to DE 04/23/2010
    25% Design 25% Package Received 01/23/2004
    25% Design Design Public Hearing 06/13/2006
    75% Design 75% Package Received 12/05/2008
    75% Design 75% Package Comments to DE 08/18/2009
    Final Design PS&E Received 06/30/2010
    Final Design PS&E to FAPRO 07/21/2010
    Consultant Contract Process NTP Issued 09/04/2003