Project Description:
MEDWAY- HIGHWAY RECONSTRUCTION, ROUTE 126 (SUMMER STREET) FROM BELLINGHAM T.L. TO HOLLISTON T.L
The total length of this full depth reclamation, signal improvement project is approximately 2.65 miles, between Village Street and the Holliston Town Line. This project will result in the construction of two 12 foot travel lanes, with 4 foot paved useable shoulders. A 5 foot bituminous concrete handicap accessible sidewalk is proposed on the west side of Summer Street for the entire length of project. Sidewalk is proposed for several sections on the east side for an approximate total length of 7000 feet. New Signals are proposed for the intersection of Summer Street (Route 126) and Milford Street (Route 109).
Location:
  • Town of Medway
  • Resident Engineer: Julio Fontecchio
    Construction Contract Value: $6,074,788.00
    Construction Bid Price: $5,046,444.25
    Initial Construction Estimate: $4,541,642.00
    District: District 3
    Current Status: Winter shut down (as of 01/27/2009)

    Contracts (1) Progress
    # 44010 -- Construction Contract
    Medway - Route 126, Summer Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/20/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Winter shut down
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/19/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Status Advertised 08/20/2005
    Project Management
    100% Design 100% Package Received 08/02/2005
    100% Design 100% Package Comments to DE 08/30/2005
    25% Design 25% Package Received 05/18/1999
    25% Design 25% Package Comments to DE 04/03/2000
    25% Design Design Public Hearing 03/09/2000
    75% Design 75% Package Received 09/04/2002
    75% Design 75% Package Comments to DE 07/14/2003
    75% Design 75% Plans Complete 07/14/2003
    Final Design PS&E Received 08/15/2005
    Final Design PS&E to FAPRO 08/15/2005