Project Description: |
TYNGSBOROUGH- LOWELL- RESURFACING & RELATED WORK ON A SECTION OF ROUTE 113 (PAWTUCKET BOULEVARD)
This project involves the resurfacing of Route 113 (Pawtucket Boulevard) from the Tyngsborough bridge to approximately the Lowell city line. The project includes the reconstruction of the headwalls for four culverts crossing Route 113 and the installation of approximately 200 feet of new sidewalk near the Lowell city line.
|
Location: |
|
Resident Engineer: | Michael Bartolo |
Construction Contract Value: | $2,314,717.75 |
Construction Bid Price: | $1,993,959.10 |
Initial Construction Estimate: | $2,358,046.00 |
District: | District 4 |
|
Bridges |
|
|
|
|