Project Description: |
ATHOL- RECONSTRUCTION AND SAFETY IMPROVEMENTS, ROUTE 2A/ROUTE 32 (MAIN STREET)
This project consists of roadway and associated improvements from the Miller’s River in the west to Petersham Road in the east, a distance of approximately 2.2 miles. Proposed work items include: roadway cold planing and full depth reconstruction, roadway horizontal and vertical alignment improvements, sidewalks, curbing, water and storm drains, signal upgrades, signage, and other associated work.
|
Location: |
|
Resident Engineer: | Ralph Romano |
Construction Contract Value: | $6,443,173.00 |
Construction Bid Price: | $5,470,728.50 |
Initial Construction Estimate: | $3,055,837.50 |
District: | District 2 |
Current Status: | Roadway under construction (as of 04/04/2007) |
Additional Info: | Work suspended for winter shutdown. When work resumes in Spring 2008, daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends. (as of 12/14/2007) |
|