Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ATHOL- RECONSTRUCTION AND SAFETY IMPROVEMENTS, ROUTE 2A/ROUTE 32 (MAIN STREET)
This project consists of roadway and associated improvements from the Miller’s River in the west to Petersham Road in the east, a distance of approximately 2.2 miles. Proposed work items include: roadway cold planing and full depth reconstruction, roadway horizontal and vertical alignment improvements, sidewalks, curbing, water and storm drains, signal upgrades, signage, and other associated work.
Location:
  • Town of Athol
  • Resident Engineer: Ralph Romano
    Construction Contract Value: $6,443,173.00
    Construction Bid Price: $5,470,728.50
    Initial Construction Estimate: $3,055,837.50
    District: District 2
    Current Status: Roadway under construction (as of 04/04/2007)
    Additional Info: Work suspended for winter shutdown. When work resumes in Spring 2008, daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends. (as of 12/14/2007)

    Contracts (1) Progress
    # 45861 -- Construction Contract
    Athol - Roadway Reconstruction and Related Work on a Section of Route 2A (Main Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/17/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Roadway under construction
    Additional Info
    Work suspended for winter shutdown. When work resumes in Spring 2008, daily lane restrictions/reductions during the work week. All lanes open at the end of the work day and weekends.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/05/1997
    Project Review Committee PRC Approved 05/06/1997
    Project Status Advertised 08/27/2005
    Project Management
    100% Design 100% Package Received 06/15/2005
    100% Design 100% Package Comments to DE 07/22/2005
    25% Design 25% Package Received 04/21/1999
    25% Design 25% Package Comments to DE 08/19/1999
    25% Design Design Public Hearing 12/14/1999
    75% Design 75% Package Received 10/19/2000
    75% Design 75% Package Comments to DE 12/05/2000
    Final Design PS&E Received 08/16/2005
    Final Design PS&E to FAPRO 08/16/2005