Project Description:
DALTON- BRIDGE REPLACEMENTS, D-01-007 & D-01-009, ROUTE 8 (HINSDALE ROAD) OVER EAST BRANCH HOUSATONIC RIVER
The purpose of this project is to replace the existing Route 8 bridges with new bridges in the existing alignment.
Location:
  • Town of Dalton
  • Resident Engineer: Hugo Pacheco
    Construction Contract Value: $4,530,253.00
    Construction Bid Price: $4,099,827.10
    Initial Construction Estimate: $2,575,000.00
    District: District 1

    Contracts (2) Progress
    # 34491 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 5 - Contract B Final
    # 52241 -- Construction Contract
    Dalton - Rte 8 (Hinsdale Road) over the E. Branch of the Housatonic River D-01-009 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/06/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    Work-Hours negotiations
    Additional effort is needed to complete the project's design. Work-hour negotiations are underway.
    Public Involvement
    Public Hearing
    A public hearing will be organized by MassHighway in the town of Dalton upon completion of the 100% design plans for the project.
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/28/1997
    Project Review Committee PRC Approved 05/06/1997
    Project Status Advertised 09/24/2005
    Project Status Advertised 09/16/2006
    Project Management
    100% Design 100% Package Received 08/17/2005
    100% Design 100% Package Comments to DE 03/22/2006
    25% Design Design Public Hearing 06/09/2005
    Final Design PS&E Received 09/12/2005
    Final Design PS&E to FAPRO 07/07/2006