STONEHAM- SIGNAL & INTERSECTION IMPROVEMENTS AT ROUTE 28/NORTH STREET
This project will address intersection deficiencies on Route 28 at two Locations: Route 28 at North Street and Route 28 at North Border and South Streets. Widening may be necessary to accommodate more traffic volume. Signal timing improvements and pavement markings will improve intersection efficiency. Route 28 at North Border Street and South Street is on the top 1000 high accident location lists.
Location:
  • Town of Stoneham
  • Construction Begins: Spring 2018
    Resident Engineer: John Lepore
    Construction Bid Price: $2,191,381.50
    District: District 4

    Contracts (4) Progress
    # 101631 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide and bridge projects, for the purpose of maintaining Final
    # 102348 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Route 28 (Main Street) at North Street. Completed
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 95334 -- Design -- Traffic Signing/Signals
    SIGNAL INSTALLATION Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/03/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/26/1997
    Project Review Committee PRC Approved 05/06/1997
    Project Status Advertised 09/23/2017
    Project Management
    100% Design 100% Package Received 03/23/2017
    100% Design 100% Package Comments to DE 05/02/2017
    25% Design 25% Package Received 03/25/2008
    25% Design 25% Package Received 07/23/2014
    25% Design 25% Package Comments to DE 07/03/2009
    25% Design 25% Package Comments to DE 12/15/2014
    25% Design Design Public Hearing 11/30/2016
    75% Design 75% Package Comments to DE 05/02/2017
    Final Design PS&E Received 07/31/2017
    Final Design PS&E to Peer Reviewer 07/31/2017
    Final Design PS&E to FAPRO 08/21/2017
    Consultant Contract Process NTP Issued 08/10/2005