Project Description: |
STONEHAM- SIGNAL & INTERSECTION IMPROVEMENTS AT ROUTE 28/NORTH STREET
This project will address intersection deficiencies on Route 28 at two Locations: Route 28 at North Street and Route 28 at North Border and South Streets. Widening may be necessary to accommodate more traffic volume. Signal timing improvements and pavement markings will improve intersection efficiency. Route 28 at North Border Street and South Street is on the top 1000 high accident location lists.
|
Location: |
|
Construction Begins: | Spring 2018 |
Resident Engineer: | John Lepore |
Construction Bid Price: | $2,191,381.50 |
District: | District 4 |
|
Bridges |
|
|
|
|