Project Description:
GARDNER- WESTMINSTER- ROUTE 140 COLD PLANE OVERLAY, BOX WIDENING, SIGNAL RECONSTRUCTION, CHANNELIZATION GREEN ST. TO SCENIC DR.
The Route 140 Roadway Improvement project begins just north of the intersection of Route 140 and Route 101 in the Town of Gardner and extends for 3.2 miles to just south of the interchange between Route 140 and Route 2 in the Town of Westminster. The project will consist of a bituminous concrete overlay and minor widening due to surface deterioration and increases in traffic. In addition, the communities of Gardner and Westminster have requested the addition of exclusive left-turn lanes at the intersections of Route 140 with: Pearl Street (Route 101), Betty Spring Road, Sargent Road, and Simplex Drive/ Route 2 westbound on/off ramps
Location:
  • City of Gardner
  • Town of Westminster
  • Resident Engineer: Steven Toloczko
    Construction Contract Value: $2,363,847.00
    Construction Bid Price: $1,958,970.00
    Initial Construction Estimate: $1,802,309.50
    District: District 3
    Current Status: Widening work on-going at Route 140 / Route101. (as of 07/08/2005)

    Contracts (1) Progress
    # 34670 -- Construction Contract
    Roadway Improvement Projects on a Section of Route 140. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/13/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Widening work on-going at Route 140 / Route101.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/24/1997
    Project Review Committee PRC Approved 02/25/1997
    Project Status Advertised 04/03/2004
    Project Management
    100% Design 100% Package Received 10/25/1999
    100% Design 100% Package Comments to DE 01/07/2000
    25% Design 25% Package Received 10/08/1998
    25% Design 25% Package Comments to DE 12/16/1998
    75% Design 75% Package Received 05/12/1999
    75% Design 75% Package Comments to DE 09/29/1999
    Final Design PS&E Received 02/27/2004
    Final Design PS&E to FAPRO 03/15/2004