Project Description:
SALEM- SIGNALIZATION & INTERSECTION IMPROVEMENTS, 7 LOCATIONS ON ROUTE 107
This project will improve the traffic signal equipment at seven signalized intersections on Route 107 so that travel delays and vehicle emissions will be reduced and traffic flow and pedestrian safety will be enhanced. The installation of an Emergency Vehicle Preemption System will provide safer access for emergency vehicles along this roadway.
Location:
  • City of Salem
  • Resident Engineer: Susan Cranney
    Construction Contract Value: $1,006,100.00
    Construction Bid Price: $746,500.00
    Initial Construction Estimate: $902,048.00
    District: District 4

    Contracts (2) Progress
    # 53055 -- Construction Contract
    Salem - Traffic Signals and Related Work at 7 Locations on Route 107 Completed
    # 99081 -- Design -- Traffic Open End
    Statewide - Assist Traffic Engineering with Traffic Control Device Improvement Projects Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/28/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/11/1997
    Project Review Committee PRC Approved 05/06/1997
    Project Status Advertised 08/05/2006
    Project Management
    100% Design 100% Package Received 08/30/2005
    100% Design 100% Package Comments to DE 11/09/2005
    25% Design 25% Package Received 08/20/1999
    25% Design 25% Package Comments to DE 11/08/2001
    25% Design Design Public Hearing 10/25/2000
    75% Design 75% Package Received 06/23/2003
    75% Design 75% Package Comments to DE 03/24/2005
    Final Design PS&E Received 01/30/2006
    Final Design PS&E to FAPRO 07/28/2006
    Consultant Contract Process NTP Issued 08/11/1997