PEABODY- BRIDGE REHABILITATION, BR# P-03-001, ROUTE 1 NB & SB OVER LOWELL STREET
This project involves the rehabilitation of the U.S. Route 1 Bridge over Lowell Street. The new bridge will cover the existing median opening between northbound and southbound travel lanes. The approach roadways will also be reconstructed. In addition, the vertical clearance of the bridge over Lowell Street will be increased.
Location:
  • City of Peabody
  • Resident Engineer: Susan Cranney
    Construction Contract Value: $2,878,000.00
    Construction Bid Price: $2,560,000.00
    Initial Construction Estimate: $2,344,687.00
    District: District 4
    Current Status: Project is 100% complete. (as of 11/29/2007)

    Contracts (1) Progress
    # 34653 -- Construction Contract
    Bridge Replacement P-03-001 (Concrete) - Route 1 (NB & SB) over Lowell Street. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/26/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is 100% complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/27/1997
    Project Review Committee PRC Approved 05/06/1997
    Project Status Advertised 09/13/2003
    Project Status Advertised 02/14/2004
    Project Management
    100% Design 100% Package Received 04/01/2003
    100% Design 100% Package Comments to DE 06/20/2003
    25% Design 25% Package Received 06/22/1999
    25% Design 25% Package Comments to DE 10/19/1999
    25% Design Design Public Hearing 03/07/2000
    75% Design 75% Package Received 03/09/2001
    75% Design 75% Package Comments to DE 10/09/2001
    Final Design PS&E Received 07/28/2003
    Final Design PS&E to FAPRO 07/31/2003