Project Description: |
LANCASTER- BRIDGE REPLACEMENT, BR# L-02-007 ROUTE 117 (MAIN STREET) OVER THE NORTH NASHUA RIVER
The work consists of replacing the existing Main Street Bridge over the Nashua River, as well as reconstruction of Main Street at the approaches.
|
Location: |
|
Resident Engineer: | Steven Toloczko |
Construction Contract Value: | $1,840,152.00 |
Construction Bid Price: | $1,766,652.00 |
Initial Construction Estimate: | $1,920,000.00 |
District: | District 3 |
|