Project Description:
DRACUT- REHABILITATION OF LAKEVIEW AVENUE
The project entails the rehabilitation of Lakeview Avenue from the intersection with Phineas Street to Tennis Plaza Road, a length of approximately 0.73 miles. The work consists of resurfacing, installation of signals at the School Complex, New Boston Road, and Phineas Street intersections, grading and drainage improvements, signs and pavement markings. New 6 foot sidewalks with granite curbing and wheelchair ramps will be constructed to facilitate student traffic to the school complex on both sides of Lakeview Avenue.
Location:
  • Town of Dracut
  • Resident Engineer: Mark Fedele
    Construction Contract Value: $2,959,360.58
    Construction Bid Price: $2,190,220.00
    Initial Construction Estimate: $2,169,580.00
    District: District 4
    Current Status: This project is is now complete. (as of 03/06/2009)

    Contracts (1) Progress
    # 43691 -- Construction Contract
    Dracut - Roadway Reconstruction and Related work on a Section of Lakeview Avenue Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/15/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is is now complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/25/1997
    Project Review Committee PRC Approved 10/07/1997
    Project Status Advertised 08/27/2005
    Project Management
    100% Design 100% Package Received 07/07/2005
    25% Design 25% Package Received 01/01/2000
    25% Design 25% Package Comments to DE 03/15/2004
    25% Design Design Public Hearing 02/26/2004
    75% Design 75% Package Received 03/14/2005
    75% Design 75% Package Comments to DE 05/17/2005
    75% Design 75% Package Rejected 12/22/2004
    Final Design PS&E Received 08/16/2005
    Final Design PS&E to FAPRO 08/16/2005