SALISBURY- RECONSTRUCTION OF ROUTE 1 (LAFAYETTE ROAD)
The purpose of this project is the reconstruction of a section of Lafayette Road in the Town of Salisbury. The project begins at Beach Road in Salisbury Square and extends northerly for approximately 2.42 mi to the New Hampshire State Line. The proposed roadway shall provide two travel lanes, shoulders, sidewalks, curbing and sidewalks with planting strips. The project will also incorporate geometric improvements to the roadway and the intersections of Route 1 & Toll road as well as Route 1 & Route 286.
Location:
  • Town of Salisbury
  • Construction Begins: Autumn 2023
    Resident Engineer: Michael Cannata
    Construction Bid Price: $18,371,000.00
    District: District 4

    Contracts (4) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 123087 -- Construction Contract
    Reconstruction of Route 1 (Lafayette Road) 23% Complete
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/10/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/28/1997
    Project Review Committee PRC Approved 05/06/1997
    Project Status Advertised 07/15/2023
    Project Management
    100% Design 100% Package Received 02/22/2022
    100% Design 100% Package Comments to DE 04/05/2022
    100% Design 100% Package Received - Resub 1 09/20/2022
    25% Design 25% Package Received 01/03/2014
    25% Design 25% Package Comments to DE 04/16/2014
    25% Design 25% Package Approved 01/06/2015
    25% Design Design Public Hearing 02/24/2015
    75% Design 75% Package Received 02/19/2021
    75% Design 75% Package Comments to DE 05/06/2021
    Final Design PS&E Received 02/02/2023
    Final Design PS&E Received - Resub 1 03/31/2023
    Final Design PS&E Received - Resub 2 05/16/2023
    Final Design PS&E Received - Resub 3 06/20/2023