SALISBURY- RECONSTRUCTION OF ROUTE 1 (LAFAYETTE ROAD)
The purpose of this project is the reconstruction of a section of Lafayette Road in the Town of Salisbury. The project begins at Beach Road in Salisbury Square and extends northerly for approximately 2.42 mi to the New Hampshire State Line. The proposed roadway shall provide two travel lanes, shoulders, sidewalks, curbing and sidewalks with planting strips. The project will also incorporate geometric improvements to the roadway and the intersections of Route 1 & Toll road as well as Route 1 & Route 286.
Location:
  • Town of Salisbury
  • Construction Begins: Autumn 2023
    Resident Engineer: Michael Cannata
    Construction Bid Price: $18,371,000.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization.
    District: District 4
    Current Status: The Contractor has mobilized. Construction signs are scheduled to be installed by mid-March. Utility Pole relocations are scheduled to begin in late February/early March. (as of 01/22/2024)

    Contracts (4) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 123087 -- Construction Contract
    Reconstruction of Route 1 (Lafayette Road) 7% Complete
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/10/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The Contractor has mobilized. Construction signs are scheduled to be installed by mid-March. Utility Pole relocations are scheduled to begin in late February/early March.
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: SALISBURY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) $19,266,283 STBG; c) AC Year 1-2 FFY 2023-2024 d) TEC = 11.72 out of 18.
  • 2024 STBG reduced from $7,665,815.00 to $504,643 via STIP Action #1.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $403,714.40
    State Cost: $100,928.60
    Total Cost: $504,643.00

    Planned Federal FY: 2024
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: SALISBURY
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) $19,266,283 STBG; c) AC Year 1-2 FFY 2023-2024 d) TEC = 11.72 out of 18.
  • 2024 HSIP Funding removed via STIP Action #1.
  • No funding records for this TIP line

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/28/1997
    Project Review Committee PRC Approved 05/06/1997
    Project Status Advertised 07/15/2023
    Project Management
    100% Design 100% Package Received 02/22/2022
    100% Design 100% Package Comments to DE 04/05/2022
    100% Design 100% Package Received - Resub 1 09/20/2022
    25% Design 25% Package Received 01/03/2014
    25% Design 25% Package Comments to DE 04/16/2014
    25% Design 25% Package Approved 01/06/2015
    25% Design Design Public Hearing 02/24/2015
    75% Design 75% Package Received 02/19/2021
    75% Design 75% Package Comments to DE 05/06/2021
    Final Design PS&E Received 02/02/2023
    Final Design PS&E Received - Resub 1 03/31/2023
    Final Design PS&E Received - Resub 2 05/16/2023
    Final Design PS&E Received - Resub 3 06/20/2023