WEST STOCKBRIDGE- BRIDGE REPLACEMENT, BR# W-22-007, ROUTE 102 OVER THE WILLIAMS RIVER
The purpose of this project is to replace the existing bridge and perform minor incidental roadway work. The proposed bridge reconstruction will be a two stage project with a temporary traffic control signal to maintain traffic across the bridge. Included in this project are guardrail, curbing and sediment controls for the Williams River.
Location:
  • Town of West Stockbridge
  • Resident Engineer: Michael Cullett
    Construction Contract Value: $1,628,193.00
    Construction Bid Price: $1,444,357.60
    Initial Construction Estimate: $899,494.70
    District: District 1
    Current Status: Contractor is doing prep work for sidewalks. (as of 05/02/2008)

    Contracts (1) Progress
    # 44196 -- Construction Contract
    West Stockbridge - Bridge Replacement Route 102 (Albany Street) over the Williams River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/30/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor is doing prep work for sidewalks.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/13/1997
    Project Review Committee PRC Approved 07/15/1997
    Project Status Approved 25% 04/16/1999
    Project Status Initiated 04/28/2005
    Project Status Advertised 09/17/2005
    Project Management
    100% Design 100% Package Received 02/28/2005
    100% Design 100% Package Comments to DE 08/27/2004
    100% Design 100% Package Comments to DE 04/27/2005
    100% Design 100% Plans Approved 08/02/2005
    25% Design 25% Package Received 02/11/1998
    25% Design 25% Package Comments to DE 06/12/1998
    25% Design 25% Package Approved 04/16/1999
    25% Design Design Public Hearing 07/28/1998
    25% Design 25% Plans Complete 08/24/1999
    75% Design 75% Package Received 02/01/1999
    75% Design 75% Package Comments to DE 06/15/2000
    Final Design PS&E Received 07/13/2005
    Final Design PS&E to FAPRO 07/22/2005
    Consultant Contract Process NTP Issued 01/09/1998