SOMERVILLE- BRIDGE REHABILITATION, S-17-005, CROSS STREET OVER THE B&M RAILROAD
The work included in this project involves the rehabilitation of the superstructure of the Cross Street bridge over B&M Railroad in Somerville. Configuration of the floor beam system will be evaluated for any potential additional vertical clearance for the railroad. The bridge deck will be replaced. Selected floor beams and stringers will be replaced. Selected gussets will be replaced. A detour will be put in place for vehicular traffic and a temporary pedestrian bridge will installed.
Location:
  • City of Somerville
  • Resident Engineer: Thomas Callery
    Construction Contract Value: $5,011,407.44
    Construction Bid Price: $4,167,485.00
    Initial Construction Estimate: $4,851,101.50
    District: District 4

    Contracts (3) Progress
    # 55034 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 64321 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 73931 -- Construction Contract
    Bridge Rehabilitation (Including Painting) (S-17-005) (Steel) Cross Street over MBTA and Pan Am Railroads. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/27/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/14/1997
    Project Review Committee PRC Approved 07/19/1997
    Project Review Committee Letter 10/01/1997
    Project Status Advertised 05/26/2012
    Project Management
    100% Design 100% Package Comments to DE 05/10/2012
    25% Design 25% Package Received 07/09/2001
    25% Design 25% Package Received 05/20/2011
    25% Design 25% Package Comments to DE 10/04/2001
    25% Design 25% Package Comments to DE 09/16/2011
    25% Design Design Public Hearing 02/27/2002
    75% Design 75% Package Received 01/20/2012
    75% Design 75% Package Comments to DE 11/07/2003
    75% Design 75% Package Comments to DE 02/27/2012
    75% Design 75% Plans Approved 03/05/2012
    75% Design 75% Plans Complete 03/05/2012
    Final Design PS&E Received 03/30/2012
    Final Design PS&E to FAPRO 05/23/2012
    Consultant Contract Process Scope to DE 12/09/2008
    Consultant Contract Process NTP Issued 04/23/2009