Project Description: |
ATTLEBORO- BRIDGE REPLACEMENT, BR# A-16-006 WATER STREET OVER THE TEN MILE RIVER
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Other |
Project Manager: | Kimberley Sloan |
Estimated Total Federal Participating Construction Cost: | $350,000.00 |
District: | District 5 |
Current Status: | This project has been advertised for construction bids. (as of 08/11/2001 ) |
|