Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHESTER- HUNTINGTON- RECONSTRUCTION, SKYLINE TRAIL SECT. III FROM THE MIDDLEFIELD TL TO COOK HILL RD / OLD CHESTER RD (7.7 MI )
The project begins at Route 23 and ends at the intersection of Huntington Road, a distance of 1.7 miles. The work consists of pavement reclamation, hot mix asphalt wearing surface, cross drain replacement, new paved waterways, dense graded crushed stone for shoulders, bituminous curbing and driveways. The installation of steel beam highway guardrail, traffic lines, and new traffic signs are also included.
Location:
  • Town of Chester
  • Town of Huntington
  • Resident Engineer: Richard Miskinis Jr
    Construction Contract Value: $4,326,890.00
    Construction Bid Price: $3,755,900.00
    Initial Construction Estimate: $3,320,191.25
    District: District 1

    Contracts (1) Progress
    # 34659 -- Construction Contract
    Roadway Reconstruction (Skyline Trail Rehabilitation Project). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/10/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 02/06/1996
    Project Status Advertised 04/03/2004
    Project Management