Project Description:
BUCKLAND- BRIDGE REPLACEMENT, BR# B-28-006, ROUTE 112 (ASHFIELD ROAD) OVER CLESSON BROOK
The purpose of this project is to replace the existing bridge with a new reinforced concrete bridge at the same location. The bridge will include painted bridge railing.
Location:
  • Town of Buckland
  • Resident Engineer: Charles Najimy
    Construction Contract Value: $1,437,182.00
    Construction Bid Price: $1,312,347.62
    Initial Construction Estimate: $1,309,589.83
    District: District 1
    Current Status: Traffic will be open to two way traffic on 11/27/06. Contractor is cleaning up project for winter. (as of 11/21/2006)

    Contracts (1) Progress
    # 38113 -- Construction Contract
    FOOTPRINT BRIDGE - BUCKLAND ROUTE 112 OVER CLESSON BROOK B-28-6 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/08/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Traffic will be open to two way traffic on 11/27/06. Contractor is cleaning up project for winter.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/03/1997
    Project Review Committee PRC Approved 07/15/1997
    Project Status Advertised 09/18/2004
    Project Management
    100% Design 100% Package Received 06/08/2004
    25% Design 25% Package Received 05/12/2004
    25% Design 25% Package Comments to DE 05/12/2004
    75% Design 75% Package Received 05/12/2004
    75% Design 75% Package Comments to DE 05/12/2004
    Final Design PS&E Received 08/27/2004
    Final Design PS&E to FAPRO 08/27/2004