Project Description: |
BUCKLAND- BRIDGE REPLACEMENT, BR# B-28-006, ROUTE 112 (ASHFIELD ROAD) OVER CLESSON BROOK
The purpose of this project is to replace the existing bridge with a new reinforced concrete bridge at the same location. The bridge will include painted bridge railing.
|
Location: |
|
Resident Engineer: | Charles Najimy |
Construction Contract Value: | $1,437,182.00 |
Construction Bid Price: | $1,312,347.62 |
Initial Construction Estimate: | $1,309,589.83 |
District: | District 1 |
Current Status: | Traffic will be open to two way traffic on 11/27/06. Contractor is cleaning up project for winter. (as of 11/21/2006) |
|