Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- ROADWAY RECONSTRUCTION ON COMMONWEALTH AVENUE FROM THE B.U. BRIDGE TO KENMORE SQ. (SEGMENT A)
This project involves the safety improvements of Commonwealth Avenue from Kenmore Square to the Boston University Bridge, a distance of approximately 0.8 miles. The project consists of the reconstruction of Commonwealth Avenue, new sidewalks and wheelchair ramps, upgrading of the existing traffic signals, geometric improvements, new street lighting, drainage improvements, landscaping and amenities.
Location:
  • City of Boston
  • Resident Engineer: John Lepore
    Construction Contract Value: $9,051,473.00
    Construction Bid Price: $12,769,642.50
    Initial Construction Estimate: $8,988,759.00
    District: District 4
    Current Status: This project is in winter shutdown. (as of 02/14/2008)

    Contracts (1) Progress
    # 43390 -- Construction Contract
    Boston - Roadway Reconstruction on a Section of Commonwealth Avenue (Segment A) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/24/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is in winter shutdown.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 05/20/1997
    Project Review Committee PRC Tabled 05/24/1999
    Project Review Committee PRC Approved 09/27/1999
    Project Status Advertised 09/20/2003
    Project Status Advertised 07/02/2005
    Project Management
    100% Design 100% Package Received 02/04/2005
    100% Design 100% Package Comments to DE 05/18/2005
    25% Design 25% Package Received 02/23/2000
    25% Design 25% Package Comments to DE 04/09/2002
    25% Design Design Public Hearing 07/08/2002
    75% Design 75% Package Received 07/22/2002
    75% Design 75% Package Comments to DE 06/20/2003
    Final Design PS&E Received 09/05/2003
    Final Design PS&E to FAPRO 09/05/2003