Project Description: |
WALPOLE- RECONSTRUCTION ON ROUTE 1A (MAIN STREET), FROM THE NORWOOD T.L. TO ROUTE 27, INCLUDES W-03-024 OVER THE NEPONSET RIVER
The proposed project consists of reconstructing 8000 feet of Route 1A including intersection and approach improvements at Fisher, Gould, North and Bullard/Willet Streets and at the Stop and Shop Plaza. The Route 1A bridge over the Neponset River, near the intersection with North Street, will be analyzed to determine if it can be rehabilitated or if it requires replacement. The limits of work are from approximately 2,000 feet north of Route 27 northerly to the Norwood town line.
|
Location: |
|
Construction Begins: | Winter 2020/2021 |
Resident Engineer: | Eric Borman![]() |
Construction Bid Price: | $19,790,903.87 |
District: | District 5 |
Current Status: | MDR: Removing existing sidewalk and curb ahead of full depth excavation operation. K. DaPonte retaining wall construction. Gravity and stone in cement mortar walls. MDR: Beginning nighttime full depth road reconstruction (5/21/23). Normal work hours are Monday through Friday 7:00 AM to 3:30 PM. Scheduled work hours are Monday through Friday 7:00AM to 3:30 PM. Expect periodic lane closures and restrictions. Roadway closed to traffic. Detour in place. (as of 05/19/2023) |
Additional Info: | Two lane traffic will be maintained from 7:00 AM to 9:00 AM, alternating one-way traffic as needed` from 9:00 AM to 3:30 PM. Night work 7:00 PM to 5:00 AM roadway closed in work area with detours in place. (as of 05/19/2023) |
|