Project Description:
WALPOLE- RECONSTRUCTION ON ROUTE 1A (MAIN STREET), FROM THE NORWOOD T.L. TO ROUTE 27, INCLUDES W-03-024 OVER THE NEPONSET RIVER
The proposed project consists of reconstructing 8000 feet of Route 1A including intersection and approach improvements at Fisher, Gould, North and Bullard/Willet Streets and at the Stop and Shop Plaza. The Route 1A bridge over the Neponset River, near the intersection with North Street, will be analyzed to determine if it can be rehabilitated or if it requires replacement. The limits of work are from approximately 2,000 feet north of Route 27 northerly to the Norwood town line.
Location:
  • Town of Walpole
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Eric Borman
    Construction Bid Price: $19,790,903.87
    District: District 5
    Current Status: MDR. Completed installation of Spear Ave. sewer bypass. Installing Rte. 1A 24 Inch drain line impacted by Spear Ave. sewer. Relocation of SMH 1-01 at NE corner of Neponset River bridge. MIG: Installation of moment slabs at MBTA bridge (work located behind barrier) Scheduled work hours are Monday through Friday 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 11/15/2024)
    Additional Info: Two lane traffic will be maintained from 7:00 AM to 9:00 AM, alternating one-way traffic as needed from 9:00 AM to 3:00 PM with police details to assist traffic through work zones. (as of 11/15/2024)

    Contracts (7) Progress
    # 112878 -- Construction Contract
    Roadway Reconstruction (Including Bridge Replacement, Culvert Extension & Signals) along a Section of Route 1A (Main Street)
    # 54716 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing preliminary, final engineering design and construction phase services for the reconstruction of Rte 1A. Final
    # 54828 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open basis for various statewide highway and bridge projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/12/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/27/1997
    Project Review Committee PRC Approved 10/07/1997
    Project Status Advertised 09/12/2020
    Project Management
    100% Design 100% Package Received 02/12/2019
    100% Design 100% Package Comments to DE 04/18/2019
    100% Design 100% Package Received - Resub 1 10/17/2019
    25% Design 25% Package Received 11/17/2000
    25% Design 25% Package Received 02/18/2011
    25% Design 25% Package Comments to DE 11/28/2014
    25% Design 25% Package Comments to DE 07/06/2015
    25% Design 25% Package Approved 02/18/2014
    25% Design Design Public Hearing 01/28/2014
    25% Design 25% Plans Complete 02/04/2014
    75% Design 75% Package Received 01/07/2016
    75% Design 75% Package Comments to DE 09/23/2016
    Final Design PS&E Received 06/30/2020
    Final Design PS&E to Peer Reviewer 07/17/2020
    Final Design Peer Review Comments to DE 08/03/2020
    Final Design PS&E Received - Resub 1 08/20/2020
    Final Design PS&E Received - Resub 3 08/28/2020
    Final Design PS&E Received - Resub 4 09/15/2020
    Consultant Contract Process Scope to DE 12/11/1997
    Consultant Contract Process NTP Issued 12/08/1999
    Consultant Contract Process Workhours Approved 07/22/1998