Project Description: |
TYNGSBOROUGH- TEMPORARY BRIDGE, T-09-001T, ROUTE 113 & 3A (KENDALL ROAD) OVER THE MERRIMACK RIVER
The work consists of constructing a temporary bridge structure adjacent to existing bridges over the Merrimac River. This bridge will carry Route 113 traffic during the rehabilitation of the existing Tyngsborough Bridge.
|
Location: |
|
Resident Engineer: | Charles Sabella |
Construction Contract Value: | $5,142,555.00 |
Construction Bid Price: | $4,464,995.00 |
Initial Construction Estimate: | $4,754,000.00 |
District: | District 4 |
Current Status: | This project is now complete. (as of 02/25/2008) |
|