Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ARLINGTON- ROADWAY RECONSTRUCTION ON A SECTION OF ROUTE 2A (SUMMER STREET)
The work consists reconstructing the roadway, constructing cement concrete sidewalks, installing granite curbing, and upgrading the existing drainage, traffic signals, traffic signs and markings.
Location:
  • Town of Arlington
  • Project Manager: Martin Leelman
    Estimated Total Contract Cost: $5,622,070.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project