CHARLEMONT- CONSTRUCTION OF A PARK AND RIDE FACILITY ON ROUTE 2
Location:
  • Town of Charlemont
  • Resident Engineer: Thomas Tierney
    Construction Contract Value: $221,118.00
    Construction Bid Price: $196,980.00
    Initial Construction Estimate: $213,000.00
    District: District 1

    Contracts (1) Progress
    # 33187 -- Construction Contract
    Construction of a Park and Ride Facility on Route 2. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/10/2003
    Contract Information
    Project Designer: In-House Boston
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/11/1997
    Project Review Committee PRC Approved 10/07/1997
    Project Status Advertised 08/24/2002
    Project Management