CANTON- DEDHAM- ROAD CONSTRUCTION INCLUDING 5 BRIDGES AT THE INTERSTATE 95 (ROUTE 128) AND 93 INTERCHANGE
This project consists of the replacement of the I-95/Route 128 bridges over the Neponset River, MBTA/Amtrak & University Avenue. It also includes adding a new travel lane and shoulder toward the median location in both directions for approximately one mile, along with the construction of auxiliary lanes and a double lane exit to I-95 South, providing safer weaving movements at the I-95 Interchange. The work also includes full depth reconstruction, new pavement, drainage improvements, construction of retaining walls, installation of new guardrail, landscaping, and a wildlife crossing under the Neponset River Bridge.
Location:
  • Town of Canton
  • Town of Dedham
  • Resident Engineer: Brian Zilinsky
    Construction Contract Value: $33,871,309.78
    Construction Bid Price: $27,454,316.60
    Initial Construction Estimate: $31,540,150.00
    District: District 4

    Contracts (1) Progress
    # 34638 -- Construction Contract
    Road Construction Including 5 Bridges at the Interstate 95 (Route 128) and 93 Interchange. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/16/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/18/1997
    Project Review Committee PRC Approved 10/07/1997
    Project Status Advertised 09/20/2003
    Project Management
    100% Design 100% Package Received 07/25/2003
    100% Design 100% Package Comments to DE 09/02/2003
    25% Design 25% Package Received 08/31/2001
    25% Design 25% Package Comments to DE 03/29/2002
    25% Design Design Public Hearing 06/19/1996
    75% Design 75% Package Received 11/05/2002
    75% Design 75% Package Comments to DE 03/04/2003
    Final Design PS&E Received 09/08/2003
    Final Design PS&E to FAPRO 09/08/2003
    Consultant Contract Process Scope to DE 11/02/1998
    Consultant Contract Process NTP Issued 10/08/1999
    Consultant Contract Process Workhours Approved 04/02/1999