Project Description:
CHARLEMONT- BRIDGE REPLACEMENT, BR# C-05-006 MOUNTAIN ROAD OVER MILL BROOK
This project will result in the demolition and replacement of the Mountain Road Bridge over Mill Brook on a new alignment, just north of its present location. The project also involves some approach roadway reconstruction.
Location:
  • Town of Charlemont
  • Resident Engineer: Thomas Tierney
    Construction Contract Value: $761,702.00
    Construction Bid Price: $641,729.92
    Initial Construction Estimate: $648,177.00
    District: District 1
    Current Status: Project Complete except for spring plantings. (as of 01/12/2005)

    Contracts (1) Progress
    # 34449 -- Construction Contract
    Bridge Replacement C-05-006 (Concrete) - Mountain Road over Mill Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/12/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project Complete except for spring plantings.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/28/1997
    Project Review Committee PRC Approved 10/07/1997
    Project Status Advertised 08/16/2003
    Project Management