Project Description:
LAWRENCE- BRIDGE REPLACEMENT, (PED) L-04-017 & (NEW) L-04-051, CANAL STREET OVER THE SPICKETT RIVER, PF #602299
A new 3-span steel arch bridge totaling 204 feet will span over the existing historical stone masonry arch bridge. The historic bridge will be rehabilitated and converted to a garden for pedestrian use. The new gateway bridge will begin at the intersection of Canal Street with Prospect and Marston Streets. At this intersection, Canal Street will have 4 travel lanes, a 6 foot median, two 5 foot sidewalks and a left turning lane from Canal Street to Prospect Street. The four lanes taper to two lanes after crossing the canal. This configuration allows two lanes of traffic to cross from Marston Street to Canal Street, and allows one lane of Prospect Street to turn right onto Canal Street and one lane of Prospect Street to turn left onto Marston Street.
Location:
  • City of Lawrence
  • Resident Engineer: Robert Bosy
    Construction Contract Value: $10,510,992.00
    Construction Bid Price: $9,081,866.00
    Initial Construction Estimate: $11,348,797.70
    District: District 4

    Contracts (5) Progress
    # 51303 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57463 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57728 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 67947 -- Construction Contract
    Construction of New Bridge (L-04-051) (Steel) and Rehabilitation of Existing Bridge (L-04-017) (Concrete) – Canal Street over the Spickett River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/08/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/11/1992
    Project Status Advertised 09/18/2010
    Project Management
    100% Design 100% Package Received 05/11/2010
    100% Design 100% Package Comments to DE 08/13/2010
    25% Design 25% Package Received 04/27/1994
    25% Design 25% Package Comments to DE 11/14/2008
    25% Design Design Public Hearing 11/16/1994
    75% Design 75% Package Received 08/04/1997
    75% Design 75% Package Received 10/21/2009
    75% Design 75% Package Comments to DE 03/22/2010
    Final Design PS&E Received 08/27/2010
    Final Design PS&E to FAPRO 08/27/2010
    Consultant Contract Process NTP Issued 12/05/2007