Project Description: |
AVON- ROADWAY RECONSTRUCTION ON WEST MAIN STREET TO BROCKTON, AVON TOWNLINE
Approximately 1,320 meters of West Main Street will be reconstructed from the Brockton townline towards downtown Avon. Sidewalks and paved shoulders will be included on both sides of the roadway. Bumpouts will be provided in limited locations to calm traffic and reduce speeds.
|
Location: |
|
Resident Engineer: | Robert Fitzgerald |
Construction Contract Value: | $3,374,318.57 |
Construction Bid Price: | $2,098,794.00 |
Initial Construction Estimate: | $2,077,527.58 |
District: | District 5 |
|