Project Description: |
WORTHINGTON- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 112
The project will resurface 9600 meters of a section of State Highway in the Town of Worthington from the intersection of Route 143 to the Huntington/Worthington town line. The project entails updates to guardrail end treatments, minor drainage improvements, placement of a leveling course and resurfacing the entire length of roadway along with replacement of all regulatory and advisory traffic signs.
|
Location: |
|
Resident Engineer: | Grant Haywood |
Construction Contract Value: | $1,941,139.00 |
Construction Bid Price: | $1,653,944.96 |
Initial Construction Estimate: | $1,462,857.50 |
Total Estimated Project Cost: | $1,653,944.96 |
District: | District 1 |
Current Status: | Contractor is replacing damaged guardrail, cleaning structures and pipe from sediment, and cleaning a few stone ditches. They will also be removing hay bales and silt fence from the project. (as of 07/05/2006) |
|
Bridges |
|
|
|
|