Project Description:
GREAT BARRINGTON- RESURFACING AND RELATED WORK ON SECTIONS OF ROUTE 7 (STOCKBRIDGE ROAD) AND ROUTE 23 (MONTEREY ROAD)
Location:
  • Town of Great Barrington
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: Other
    Project Manager: Albert Li
    Estimated Total Federal Participating Construction Cost: $1,226,427.25
    District: District 1
    Current Status: This project has been advertised for construction bids. (as of 06/12/2004 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/20/1997
    Project Review Committee PRC Approved 10/07/1997
    Project Status Advertised 09/14/2002
    Project Status Advertised 06/12/2004
    Project Management
    Final Design PS&E Received 05/17/2004
    Final Design PS&E to FAPRO 05/17/2004