CHESTER- HUNTINGTON- RESURFACING & RELATED WORK ON ROUTE 20 (FROM MM36 , CHESTER, TO MM42.6, HUNTINGTON)
The project will resurface 6.8 miles of State Highway Route 20 from Mile Marker 36 in the Town of Chester to the Huntington/Russell Town Line. The works also includes drainage improvements, installation of a new drainage trunk line in the center of Huntington, curbing, sidewalks, traffic sign replacement and new pavement markings.
Location:
  • Town of Chester
  • Town of Huntington
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Albert Li
    Estimated Total Contract Cost: $4,273,339.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project