Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BUCKLAND- CHARLEMONT- RESURFACING & RELATED WORK ON ROUTE 2, FROM MM 27.41 (R.R. BRIDGE) TO MM 37.39 (BUCKLAND/SHELBURNE T.L.) EXCLUDING MM 29.5 TO MM 30.75 (VILLAGE CENTER)
This 8.73 mile project consists of resurfacing Route 2 (NHS), along with minor drainage improvements; guardrail, signage, and pavement marking upgrades, and other incidental work as needed.
Location:
  • Town of Buckland
  • Town of Charlemont
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Eamon Kernan
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • C05018 
    • C05025 
    See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project