| Project Description: |
BUCKLAND- CHARLEMONT- RESURFACING & RELATED WORK ON ROUTE 2, FROM MM 27.41 (R.R. BRIDGE) TO MM 37.39 (BUCKLAND/SHELBURNE T.L.) EXCLUDING MM 29.5 TO MM 30.75 (VILLAGE CENTER)
This 8.73 mile project consists of resurfacing Route 2 (NHS), along with minor drainage improvements; guardrail, signage, and pavement marking upgrades, and other incidental work as needed.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Eamon Kernan![]() |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 1 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||