Project Description: |
NORTHFIELD- BRIDGE REPLACEMENT, N-22-010, BIRNAM ROAD OVER MILL BROOK
The purpose of this project is to replace and widen the existing bridge and improve the transition of the approach roadway width into the new bridge. The bridge will be closed during construction and a detour will be provided. There existing bridge will remain with no sidewalks.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Construction Begins: | Winter 2026/2027 |
Project Manager: | Anthony Christakis![]() |
Estimated Total Contract Cost: | $5,198,500.00 |
Estimated Total Federal Participating Construction Cost: | $5,572,040.00 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Franklin Regional Council of Governments. |
District: | District 2 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 03/10/2023 ) |
|